With the weather warming, look for more road construction projects underway in and around Fishers. There will be work starting on some new roundabouts and many other updates of interest in this latest message.
Here is the listing, for the work week beginning Monday, April 28, as provided by the City of Fishers:
========
As of Monday (3/10), the contractor has begun reconstruction and interchange tie in on the west side of 141st street. To do this work as quickly as possible, this will require 141st St. to be closed on the west side. The closure will be in place from SR37 thru and west of Trade Center Dr. This work will involve new curbs, medians, storm sewer, subgrade treatment and pavement. See business access map here.
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
the next phase of construction. Traffic has transitioned to the eastside,
with SR37 north and southbound lanes remaining open. Please review
detour routes to plan ahead during this time. Thank you for your continued
patience and remember to drive cautiously and safely through construction
areas. View a detour for E 141st Street and SR37 here, view the
West detour here and East detour here.
CLEAR PATH IMPROVEMENT PROJECT
Friday, April 25 (9 p.m. to 6 a.m.)
Friday, April 25 (9 p.m.) to Monday, April 28 (6 a.m.)
A mobile shoulder cleaning operation is scheduled overnight Thursday, April 24, through Saturday, April 26, from 9 p.m. to 6 a.m. Long-Term Closures
82nd Street Ramps For detour routes and additional project information, visit clearpath465.com. |
|||||
121ST STREET AND HOOSIER ROAD – FUTURE ROUNDABOUT
Drivers can expect to see more construction activity at this intersection as the contractor works on utility relocation – keep an eye out for periodic lane restrictions Monday – Friday 9AM – 3PM
131ST STREET AND HOWE ROAD – FUTURE ROUNDABOUT
Drivers can expect to see more construction activity at this intersection as the contractor works on utility relocation – keep an eye out for periodic lane restrictions Monday – Friday 9AM – 3PM.
ROAD RESTRICTION ON SUNBLEST BLVD AT LANTERN ROAD
The contractor will require a two-day closure of Sunblest Blvd at Lantern Road starting after 9 am on Monday, April 28, possibly lasting until Tuesday evening. This will impact bus routes. Barricades will be at Sunblest Blvd and Ellipse Pkwy, but buses should be able to access stops between Ellipse and Lantern. Updates will be provided if the road reopens sooner. Go here for an ariel view of the closure.
136TH STREET WIDENING – ROAD CLOSURE
As of Tuesday, April 1, 136th Street between Prairie Baptist Road and Cyntheanne Road has been closed to through traffic as construction begins on the reconstruction of the roadway. Access to all of the homes and fire station off of 136th Street will be maintained only to eastbound traffic. Westbound traffic will need to follow the attached detour route. Access into Hunters Run and Silverton will be off of Prairie Baptist or Cyntheanne Road. See a map of this closure here.
SOUTHEASTERN PARKWAY RESTRICTIONS
Beginning on or after April 21st, expect to see lane restrictions along Southeastern Parkway, Cyntheanne Road and 126th Street as utilities perform aerial work along the roadway. Flaggers will be in place between 9AM and 3PM.
96TH STREET AND THE NICKEL PLATE TRAIL
The 96th & Allisonville roundabout is now open and accessible in all directions, making travel smoother and safer at one of the main gateways to our City. Please proceed with caution as this is still an active construction site. Expect lane restrictions in all directions on Tuesday April 29th between 9am and 3pm.
On Wednesday April 30th there will be overnight lane restrictions in place from 9pm-6am in all directions.
2025 ROAD RESURFACING PROJECT
Beginning on Monday, May 5th our contractor will begin curb and curb ramp work in the Sawgrass Subdivision. Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. For additional project information, view the Capital Project Dashboard here.
View the Road Resurface Overview Map here.
The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation, Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. Click here for an aerial view. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.