Fishers area road construction update for the week of April 7

Road work in and around Fishers is ramping up as we head into the month of April.  Plenty of items are on the weekly listing,

Here is the official update for the work week starting Monday, April 7, as provided by the City of Fishers:

STATE ROAD 37 IMPROVEMENT PROJECT

As of Monday (3/10),  the contractor has begun reconstruction and interchange tie in on the west side of 141st street. To do this work as quickly as possible, this will require 141st St. to be closed on the west side. The closure will be in place from SR37 thru and west of Trade Center Dr. This work will involve new curbs, medians, storm sewer, subgrade treatment and pavement. See business access map here.

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com

STATE ROAD 37 AND 141ST STREET

 

Find construction updates at 37thrives.com and follow
DriveFishers on X as work progresses.

The westside of 141st St. at SR37 has closed for
the next phase of construction.  Traffic has transitioned to the eastside,
with SR37 north and southbound lanes remaining open. Please review
detour routes to plan ahead during this time.  Thank you for your continued
patience and remember to drive cautiously and safely through construction
areas.  View a detour for E 141st Street and SR37 here, view the
West detour here  and East detour here.
CLEAR PATH IMPROVEMENT PROJECT


To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com 

I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.

Long-Term Closures

  • Ramp from 56th Street to I-465
  • Ramp from Allisonville Road to I-465 eastbound
  • Ramp from northbound Binford Boulevard to I-465 westbound

82nd Street Ramps

For detour routes and additional project information, visit clearpath465.com.

PROJECTS NORTH OF 116TH STREET


146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT

Please use extreme caution and follow the 35mph posted speed limit when traveling through the work zone. Left turns are prohibited in all directions at the intersection. Please see the included intersection diagram for the movements that are allowed. Periodic lane closures and intermittent stoppages may be necessary to complete certain work items. Please watch for flaggers and workers in and around the construction zone. The next traffic phasing switch is anticipated to occur in December.
 Bridge crews are continuing work on the widening of the eastbound bridge over the White River. The contractor is continuing to work on storm sewer installation, subgrade preparation, and paving operations. Bridge and MSE wall construction at the intersection is ongoing between the eastbound and westbound travel lanes. The contractor is working on the roundabout construction and installing barrier wall within the construction zone. The contractor anticipates working on seeding and sodding in the coming weeks. Construction vehicles will be entering and exiting from this work area, so please be vigilant and follow the 35mph posted speed limit when driving through the construction zone.
Anticipated Completion Date: August 1, 2025
 For additional project information, visit the 146th Street & Allisonville Rd. Project Page.

136TH STREET WIDENING – ROAD CLOSURE

Beginning on Tuesday, April 1, 136th Street between Prairie Baptist Road and Cyntheanne Road will be closed to through traffic as construction begins on the reconstruction of the roadway.  Access to all of the homes and fire station off of 136th Street will be maintained only to eastbound traffic.  Westbound traffic will need to follow the attached detour route.  Access into Hunters Run and Silverton will be off of Prairie Baptist or Cyntheanne Road.  See a map of this closure here.

UTILITY WORK ON SUNBLEST AVENUE
Beginning on March 14 the contractor will begin setting up for a water line installation, keep an eye out for a restriction on the right turn lane onto Lantern Road. Drivers will still be able to turn right onto Lantern. Please proceed with caution through this intersection.
PROJECTS SOUTH OF 116TH STREET

UTILITY WORK ON SOUTH STREET AND LANTERN ROAD
Please be advised that beginning April 7, the contractor will be closing Lantern Road between 116th and South Street, in order to conduct utilility work in the area for the District South/CityView Developments. This closure is expected to last three days and is weather permitting. See map of closure here.

NICKEL PLATE TRAIL CLOSURE
For installation of the NPT 116th Street tunnel lights and NPT pedestrian trail mural painting, the trail will require closure for the week of April 7. The train platform stairs and the monumental stairs will remain open.

BRIGHTSPEED FIBER INSTALLATION
Brightspeed will be installing fiber throughout the following neighborhoods: Bridger Pines, Bridger Pines West and Arbor Pines. Work will be conducted in the utility easement behind the sidewalk.

96TH STREET AND THE NICKEL PLATE TRAIL
Please look out for intermittant lane restrictions (east and west bound) between Hague road and the entrance to Menards between 9am and 3PM, proceed through the area with caution.

96TH STREET AND ALLISONVILLE ROAD INTERSECTION
The 96th & Allisonville roundabout is now open and accessible in all directions, making travel smoother and safer at one of the main gateways to our City. Please proceed with caution as this is still an active construction site. Be on the look out for intermittant lane restrictions.

NICKEL PLATE TRAIL AND 82ND ST CLOSURE – INDIANAPOLIS PROJECT
Starting April 7, a closure will be placed on 82nd Street between Craig Street and Castleton Road for Nickel Plate Trail construction. The closure is anticipated to be in place until April 15. Businesses in the area will remain accessible to the public. See detour map here

HERITAGE PARK BRIDGE – TRAIL CLOSURE
The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation, Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. Click here for an ariel view. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.