As we get further into March, road construction ramps up once again in our area.
First, one update that did not make this listing is the 146th Street and Allisonville Road Hamilton County project. Watch for more lane closures in coming weeks as material deliveries ramp up at that construction site.
Also, there is a road closure to the west of State Road 37 on 141st Street.
There are a number of other projects and lane closures in this week’s update.
Here is the list for the work week starting Monday, March 17, as provided by the City of Fishers:
*LANE CLOSURE UPDATE*
As of Monday (3/10), the contractor has begun reconstruction and interchange tie in on the west side of 141st street. To do this work as quickly as possible, this will require 141st St. to be closed on the west side. The closure will be in place from SR37 thru and west of Trade Center Dr. This work will involve new curbs, medians, storm sewer, subgrade treatment and pavement. See business access map here.
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
Find construction updates at 37thrives.com and follow DriveFishers on X as work progresses.
the next phase of construction. Traffic has transitioned to the eastside,
with SR37 north and southbound lanes remaining open. Please review
detour routes to plan ahead during this time. Thank you for your continued
patience and remember to drive cautiously and safely through construction
areas. View a detour for E 141st Street and SR37 here, view the
West detour here and East detour here.
To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.
Long-Term Closures
- Ramp from 56th Street to I-465
- Ramp from Allisonville Road to I-465 eastbound
- Ramp from northbound Binford Boulevard to I-465 westbound
82nd Street Ramps
- Ramp from I-69 South to 82nd Street is now open
- Ramp from 82nd Street to I-69 South is open only to I-465 South
- 82nd Street ramps – current configuration
For detour routes and additional project information, visit clearpath465.com.
On the week of March 17 the contractor will be doing utility work on Southeastern Parkway between Cyntheanne Road and N 113th Street. Proceed through the area with caution – work will go from 9am to 3 pm.
PROJECTS NORTH OF 116TH STREET
Please be advised, as of Wednesday, February 5,2025, the contractor has implemented a traffic phase shift for eastbound 146th Street. Traffic has been shifted to the south and will now utilize the bridge carrying eastbound 146th Street over the White River. The contractor will utilize construction barrels to delineate the driving area from the construction zone. See graphic below for the new lane configuration.
UTILITY WORK ON SUNBLEST AVENUE
Beginning on March 14 the contractor will begin setting up for a water line installation that will take place over the weekend, keep an eye out for a restriction on the right turn lane onto Lantern Road. Drivers will still be able to turn right onto Lantern. Please proceed with caution through this intersection.
PROJECTS SOUTH OF 116TH STREET
UTILITY WORK ON SOUTH STREET
Watch out for intermittent lane restrictions on South Street and Lantern Road these will be in place from 9am to 3pm. The contractor will be conducting utilility work in the area for the District South/CityView Developments.
BRIGHTSPEED FIBER INSTALLATION
Brightspeed will be installing fiber throughout the following neighborhoods: Bridger Pines, Bridger Pines West and Arbor Pines. Work will be conducted in the utility easement behind the sidewalk.
96TH STREET AND THE NICKEL PLATE TRAIL – UTLITY WORK WITH OVERNIGHT LANE CLOSURE
On the week of March 17 there will be an overnight lane closure on Westbound lanes of 96th street between the entrance to Menards and Hague Rd . This closure will go from March 19 to March 21 beginning at 9pm and ending at 6am the following day.
96TH STREET AND ALLISONVILLE ROAD INTERSECTION
The 96th & Allisonville roundabout is now open and accessible in all directions, making travel smoother and safer at one of the main gateways to our City. Please proceed with caution as this is still an active construction site. Be on the look out for intermittent lane restrictions.