Road construction update for the week ahead

The road construction report is getting shorter, but there are the usual updates on ongoing projects.  Looks for sidewalk work in the coming week in the Avalon and Meadow Brook neighborhoods.

Here is the update, for the work week starting Monday, December 9:

============

STATE ROAD 37 IMPROVEMENT PROJECT


To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com
***STATE ROAD 37 AND 141ST STREET – TRAFFIC UPDATE***

*
On Friday, December 20th, the contractor will be conducting patch work operations on SR37 near the 141st St. interchange.  During this time there will be short-term closures and lane restrictions between the hours of 9AM-3PM.  The work will begin on the northbound lanes of SR37, followed by the southbound lanes.  *

Find construction updates at 37thrives.com and follow
DriveFishers on X as work progresses.
As of July 23rd, the westside of 141st St. at SR37 has closed for
the next phase of construction.  Traffic has transitioned to the eastside,
with SR37 north and southbound lanes remaining open. This closure
will remain in place throughout 2024.  Please review detour routes to
plan ahead during this time.  Thank you for your continued patience
and remember to drive cautiously and safely through construction
areas.  View a detour for E 141st Street and SR37 here, view the
West detour here  and East detour here.
CLEAR PATH IMPROVEMENT PROJECT


To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com 
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.

Long-Term Closures

  • Ramp from 56th Street to I-465
  • Ramp from Allisonville Road to I-465 eastbound
  • Ramp from northbound Binford Boulevard to I-465 westbound

82nd Street Ramps

For detour routes and additional project information, visit clearpath465.com.

SIDEWALK IMPROVEMENT PROJECT

Howard Companies is going to be conducting sidewalk repair improvements in the Avalon Neighborhood beginning December 9 and CC&T will be continuing sidewalk repairs in Meadow Brook the same week. The sidewalk work will consist of removal and replacement of sidewalk panels which pose a toe kick trip hazard. Sidewalk within driveways is not included in the scope of this project.

PROJECTS NORTH OF 116TH STREET

146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT 

*TRAFFIC PATTERN UPDATE *

Please be advised, beginning on or after Thursday, December 19th, the contractor will implement a traffic phase shift for eastbound 146th Street. Traffic will be shifted to the south and will now utilize the bridge carrying eastbound 146th Street over the White River. The contractor will utilize construction barrels to delineate the driving area from the construction zone.

Please use extreme caution when driving in this area and watch for flaggers during the phase shift.

Please use extreme caution and follow the 35mph posted speed limit when traveling through the work zone. Left turns are prohibited in all directions at the intersection. Please see the included intersection diagram here, for the movements that are allowed. Periodic lane closures and intermittent stoppages may be necessary to complete certain work items. Please watch for flaggers and workers in and around the construction zone.

 For additional project information, visit the 146th Street & Allisonville Rd. Project Page.

 

 

PROJECTS SOUTH OF 116TH STREET
96TH STREET AND ALLISONVILLE ROAD INTERSECTION

*TRAFFIC PATTERN UPDATE ON ALLISONVILLE & 96TH ST*

The 96th & Allisonville roundabout is now open and accessible in all directions, making travel smoother and safer at one of the main gateways to our City. Please proceed through with caution as this is still an active construction site*Watch out for lane restrictions in the coming week – the contractor will be working on signal and pavement work.*


HERITAGE PARK BRIDGE – TRAIL CLOSURE 

The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation, Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. To construct this bridge, the contractor will need to restrict access to a portion of Heritage Park’s loop trail that runs adjacent to the river through the woods beginning the week of March 4, click here for an ariel view. During this time, you’ll notice temporary construction fencing going up as we prepare for construction. Beginning the week of March 11, the contractor will work to clear the necessary trees between the park and river. Bridge construction will follow beginning in May. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.