Lots of road construction news in the latest update

The weather may have turned more like winter, but there remains a long list of road construction updates for the Fishers area.  Lots of restrictions and changes coming to the Clear Path construction site on I-69 near I-465.  Also, look for lane restrictions on 96th Street.

This is one update you may want to check carefully, below, as provided by the City of Fishers:

STATE ROAD 37 IMPROVEMENT PROJECT


To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com
***STATE ROAD 37 AND 141ST STREET – TRAFFIC UPDATE***

*As of Thursday, November 7, traffic has gone back to two lanes open both north and southbound along SR37. *

Find construction updates at 37thrives.com and follow
DriveFishers on X as work progresses.
As of July 23rd, the westside of 141st St. at SR37 has closed for
the next phase of construction.  Traffic has transitioned to the eastside,
with SR37 north and southbound lanes remaining open. This closure
will remain in place throughout 2024.  Please review detour routes to
plan ahead during this time.  Thank you for your continued patience
and remember to drive cautiously and safely through construction
areas.  View a detour for E 141st Street and SR37 here, view the
West detour here  and East detour here.
CLEAR PATH IMPROVEMENT PROJECT


To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com 
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.

Short-Term Closures

Upcoming Weekend:
Friday, Dec. 6 through Monday, Dec. 9 (Expected to reopen by 6 a.m. Monday)

  • I-69 South single lane open
  • Ramp from 96th Street to I-69 South closed
  • Ramp from 106th Street to I-69 SB closed (Starting at 11 p.m.)
  • Ramp from I-69 South to I-465 South closed (Starting at 11 p.m. and expected to reopen Sunday, Dec. 8 around 12 p.m.)

Long-Term Closures

  • Ramp from 56th Street to I-465
  • Ramp from Allisonville Road to I-465 eastbound
  • Ramp from northbound Binford Boulevard to I-465 westbound

82nd Street Ramps

Temporary Express Lane

For detour routes and additional project information, visit clearpath465.com.

SIDEWALK IMPROVEMENT PROJECT

Howard Companies is going to be conducting sidewalk repair improvements in the Avalon Neighborhood beginning December 9 and CC&T will be continuing sidewalk repairs in Meadow Brook the same week. The sidewalk work will consist of removal and replacement of sidewalk panels which pose a toe kick trip hazard. Sidewalk within driveways is not included in the scope of this project.

PROJECTS NORTH OF 116TH STREET
146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT 

Please use extreme caution and follow the 35mph posted speed limit when traveling through the work zone. Left turns are prohibited in all directions at the intersection. Please see the included intersection diagram here, for the movements that are allowed. Periodic lane closures and intermittent stoppages may be necessary to complete certain work items. Please watch for flaggers and workers in and around the construction zone. The next traffic phasing switch is anticipated to occur in December.

Bridge crews are continuing work on the widening of the eastbound bridge over the White River. The contractor is continuing to work on storm sewer installation, sub-grade preparation, and paving operations. Bridge and MSE wall construction at the intersection is ongoing between the eastbound and westbound travel lanes. The contractor is working on the roundabout construction and installing barrier wall within the construction zone. The contractor anticipates working on seeding and sodding in the coming weeks. Construction vehicles will be entering and exiting from this work area, so please be vigilant and follow the 35mph posted speed limit when driving through the construction zone.

For additional project information, visit the 146th Street & Allisonville Rd. Project Page.

 

141ST AND PRAIRIE LAKES ROUNDABOUT –  NOW OPEN

This roundabout is now open to traffic as of Wednesday November 27 – please keep in mind this will remain an active construction site so please proceed with caution as the contractor completes final punchlist items. We appreciate your patience!

PROJECTS SOUTH OF 116TH STREET
96TH STREET BEAUTIFICATION
The contractor will be finishing up some details on the lighting for this project on the week of December 9. This project consists of decorative streetlights being installed along 96th Street from North by Northeast Blvd to Cumberland Road. New medians have been installed along North by Northeast Blvd and Kincaid Blvd with streetlights. Watch out for lane restrictions on North by Northeast to Kincaid Avenue from 9am-3pm. There could also be intermittent lane restrictions on 96th street as public works completes landscaping. For more details visit our Capital Projects Dashboard here.96TH STREET LANE RESTRICTIONS

Beginning at 9 am til 5 pm on Monday, Dec. 9th, there will be lane restrictions on westbound 96th Street just west of the railroad tracks. There will be lane shifts throughout the day in this area so please drive with caution.
Beginning at 9 am on Tuesday, Dec. 10th, there will be lane restrictions on westbound 96th Street just west of the railroad tracks.
There will be lane there will be lane restrictions on westbound 96th Street just west of the railroad tracks starting at 9 am on Wednesday, Dec. 11th. There will be lane shifts throughout the day in this area so please drive with caution.
There will be lane there will be lane restrictions on westbound 96th Street just west of the railroad tracks starting at 9 am on Monday, Dec. 16th. There will be lane shifts throughout the day in this area so please drive with caution.
There will also be a lane restriction on eastbound 96th Street between Sam’s Club and the railroad tracks from Dec. 9th through Dec. 16th.

This work is weather permitting as this is asphalt and concrete work.  If weather prevents the scheduled days work, the schedule will be pushed one day.
 
96TH STREET AND ALLISONVILLE ROAD INTERSECTION

*TRAFFIC PATTERN UPDATE ON ALLISONVILLE & 96TH ST*

The 96th & Allisonville roundabout is now open and accessible in all directions, making travel smoother and safer at one of the main gateways to our City. Please proceed through with caution as this is still an active construction site*Watch out for lane restrictions in the coming week – the contractor will be working on signal and pavement work.*

Huge thanks to our dedicated construction crews and the Fishers Engineering team for their hard work in bringing this project to completion! Please note that some lane restrictions will remain as crews wrap up the final touches. Thank you, Fishers, for your patience throughout this project.


HERITAGE PARK BRIDGE – TRAIL CLOSURE 

The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation, Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. To construct this bridge, the contractor will need to restrict access to a portion of Heritage Park’s loop trail that runs adjacent to the river through the woods beginning the week of March 4, click here for an ariel view. During this time, you’ll notice temporary construction fencing going up as we prepare for construction. Beginning the week of March 11, the contractor will work to clear the necessary trees between the park and river. Bridge construction will follow beginning in May. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.