Watch for a change in the traffic pattern at the 96th Street & Allisonville Road construction site. Fishers says the roundabout should be fully open to traffic by late October/early November.
Here is the full listing, as provided by the City of Fishers:
========
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
***STATE ROAD 37 AND 141ST STREET – TRAFFIC UPDATE***
As of Monday, September 9 the NB lane of SR37 has been down to one lane to allow for construction of the deep storm sewer.
The State Road 37 Improvement Project is in its final interchange with construction of the 141st Street and State Road 37 now underway. During this time, all traffic is accessible via the eastside, with north and south bound lanes open at all times on SR37View detour routes here.
Find construction updates at 37thrives.com and follow DriveFishers on X as work progresses.
the next phase of construction. Traffic has transitioned to the eastside,
with SR37 north and southbound lanes remaining open. This closure
will remain in place throughout 2024. Please review detour routes to
plan ahead during this time. Thank you for your continued patience
and remember to drive cautiously and safely through construction
areas. View a detour for E 141st Street and SR37 here, view the
West detour here and East detour here.
WHAT TO EXPECT THIS SUMMER
The current phase is construction on the west side of 141st. During this time, all traffic has been moved to the east side, with north and south bound lanes open at all times on SR37 (intermittent restrictions will be communicated). All construction updates will be posted to DriveFishers on X(Twitter) and 37Thrives on Facebook. Please visit 37thrives.com to sign-up for email updates.
To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com
I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.
Long-Term Closures
- Ramp from 56th Street to I-465
- Ramp from Allisonville Road to I-465 eastbound
- Ramp from northbound Binford Boulevard to I-465 westbound
- 71st Street under I-465
82nd Street Ramps
- Ramp from I-69 South to 82nd Street closed
- Ramp from 82nd Street to I-69 South closed
82nd Street ramp to I-69 South lane restrictions
- No access to Binford Boulevard or I-465 West from 82nd Street to I-69 South
For detour routes and additional project information, visit clearpath465.com.
For additional project information, visit the 146th Street & Allisonville Rd. Project Page.
Public Works will be completing Phase 2 of the reconstruction of Florida Road between Southeastern PKY and E 113th Street from September 18- October 4. A portion of the road south of Whelchel Dr will be closed and the rest of the road will be open to local traffic only. See a map of phase 2 here.
Construction crews have begun preliminary work for the construction of a new roundabout at the intersection of 141st Street and Prairie Lakes Blvd/Old Oak lane. As of August 19th, the intersection has been closed to through traffic. Access to Woods of Britton apartments will be maintained off of Cumberland Road only during this first phase. The 141st Street access to Prairie Lakes will be closed and access will be off of Cumberland Road and 146th Street. View map here.
- Business Access: Businesses along Mundy Drive remain accessible from SR37 and 141st Street. A right in, right out configuration will continue at the intersection.
- Prairie Lakes Residents: Access your complex via Cumberland Road or 146th Street. Access at 141st Street will be closed.
- Woods of Britton Residents: Use Cumberland Road to access 141st Street, access to your complex along 141st Street will remain open. Exiting the complex, you may only travel east (right) on 141st Street towards Cumberland Road.
Please see the attached map for detour routes.
This roundabout is now open but remains an active construction site with intermittant lane restrictions. During the week of September 30 and weather permitting the contractor will be working on striping Corydon Dr., which will soon serve as the new connection for the Hunters Run development, anticipated to open in October of this year. The project will rehabilitate or reconstruct the pavement, add curb and gutter with storm sewers, and multi-use paths and/or bicycle lanes. Click here for an ariel view of the roundabout and for more information visit our Capital Projects Dashboard.
The contractor will be working on landscaping and lighting for this project on the week of September 30. This project consists of decorative streetlights being installed along 96th Street from North by Northeast Blvd to Cumberland Road. New medians will also be installed along North by Northeast Blvd and Kincaid Blvd with streetlights. Watch out for lane restrictions on North by Northeast from 9am-3pm. For more details visit our Capital Projects Dashboard here.
UTILITY WORK ON SOUTH STREET
There will be lane restrictions on South Street, between the Nickel Plate Trail and Lantern Road, starting on Wednesday, Sept. 17th to allow for utility installation. Flaggers will be in place to help direct traffic in this area.
ROAD CLOSURE – 96TH STREET AND ALLISONVILLE ROAD INTERSECTION
*TRAFFIC PATTERN UPDATE ON ALLISONVILLE & 96TH ST*
- Northbound traffic on Allisonville Road can continue north or turn east onto 96th Street.
- Southbound traffic on Allisonville Road can continue south or turn west onto 96th Street.
- Eastbound traffic on 96th Street will have a right turn-only option to travel southbound on Allisonville Road.
- Westbound traffic on 96th Street will have a right turn only option to travel northbound on Allisonville Road.
Phase 3B
As of July 23rd, the contractor has transitioned to phase 3B, traffic has shifted from the east side of Allisonville to the west and will continue to flow North and South. At this time the driveway for Circle K constructed in phase 3A will be accessible. View a map here.
On April 1st,construction began on the 96th St. & Allisonville Rd. Roundabout project This project aims to enhance connectivity along this stretch of the Allisonville Corridor. The existing Michigan Left intersection was eliminated and transitioned to a two-lane roundabout adjacent to the new River Place development. This project is slated to be completed at the end of the year, with minor enhancements completed in the Spring of 2025. You can view a close up map of what the roundabout will look like after April 9 here.
Closures – After April 9, 2024
- 96th Street is closed from Allisonville Road to Hazel Dell Pkwy.
- Southbound traffic cannot turn left onto 96th St from Allisonville Rd.
- Allisonville Rd is open to one lane at 96th Street for North and South bound traffic.
- All access to local businesses remains open.
- See suggested detour maps at 96th & Allisonville Rd Roundabout
We are in constant communication with the County on our traffic signals along 116th Street and working towards accomodating the increased traffic due to this detour. We are aware of the increased volumes due to this project and neighboring ones as well.
Please be advised, 106th Street between Cumberland Road and Hamilton Pass has been closed to all thru traffic for a bridge replacement project. The anticipated roadway reopening date is Friday, October 18, 2024.
Local traffic will continue to have access to their homes, while thru traffic is asked to utilize the posted detour route of Cumberland Road, 96th Street, and Mollenkopf Road. For more details visit the Hamilton County page.
HERITAGE PARK BRIDGE – TRAIL CLOSURE