Fishers area road construction update for the week of Monday, June 17

This will be another busy week for road construction crews.  Allisonville Road is now open north and south at 146th Street, but no left turns are allowed.  This will lead to the construction beginning at 141st Street and State Road 37, so be alert to lane restrictions in that area.

Below is the full weekly road construction report, as provided by the City of Fishers:

STATE ROAD 37 IMPROVEMENT PROJECT


To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com

STATE ROAD 37 AND 141ST STREET

The final interchange of the State Road 37 Improvement Project will officially begin construction at 141st St. and State Road 37 this summer. One important note: To ease the construction burden in the area, the work will not begin until Hamilton County’s 146th St. closure at Allisonville re-opens. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Spring 2024. View detour routes here.

ROADWORK UPDATE 

On/after June 5th preliminary construction work will begin at SR37 & 141st Street.  During this time pavement markings and concrete barriers will be placed.  There will be no closures during this phase, only intermittent lane restrictions during the hours of 9AM-3PM.

Find construction updates at 37thrives.com and follow DriveFishers on X as work progresses.

WHAT TO EXPECT THIS SUMMER

The interim traffic configuration that has been in place will be adjusted to accommodate temporary pavement construction leading up to the next phase of construction. The next phase will be construction on the west side of 141st.  During this time, all traffic will be moved to the east side, with north and south bound lanes open at all times on SR37 (intermittent restrictions will be communicated). All construction updates will be posted to DriveFishers on X(Twitter) and 37Thrives on Facebook.  Please visit 37thrives.com to sign-up for email updates.

To navigate the merge, remember:

  • Use the accel lane to gain speed, not stop
  • Use your mirrors and pay attention
  • Look for a gap in SR 37 traffic and safely merge

 

CLEAR PATH IMPROVEMENT PROJECT


To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com 

I-465 & I-69
Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open.

Short-Term Closures

Friday, June 14 (9 p.m. to 6 a.m.)

  • Single lane closures on I-465 North to I-465 West to install signage from 75th Street to 82nd Street

Friday, June 14 (9 p.m.) to Sunday, June 16 (6 a.m.)

  • Two lane closure on I-465 North to I-465 West to install barrier wall and striping
  • Single lane closure on ramp from I-465 North to I-69 North

Ramp Closure (Friday, June 14 at 11 p.m. to 4 a.m.)

  • 82nd Street ramp to I-69 North closed

 

Long-Term Closures

  • Ramp from 56th Street to I-465
  • Ramp from Allisonville Road to I-465 eastbound
  • Ramp from northbound Binford Boulevard to I-465 westbound
  • 71st Street under I-465

82nd Street Ramps

  • Ramp from I-69 South to 82nd Street closed
  • Ramp from 82nd Street to I-69 South closed

82nd Street ramp to I-69 South lane restrictions

Temporary Express Lane

82nd Street Ramp to I-69 Northbound Now Open

I-69 Northbound to 82nd Street Ramp Closure

For detour routes and additional project information, visit clearpath465.com.

 

PROJECTS NORTH OF 116TH STREET

 

146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT 
As of Sunday, June 9th at 6:00 PM Allisonville Road north & south at 146th street has reopened.

The intersection will utilize a temporary signal during this next phase. Please use caution and be aware of the signal when traveling through the intersection. No left turns will be permitted at the intersection. Please see the included intersection diagram below for the movements that are allowed.

The temporary signal at Greenfield Ave. and Herriman Blvd. will be removed after Allisonville Road is reopened to traffic. See a map here.

Please use extreme caution while driving through this construction zone. There has been a lot of traffic going above the posted speed limit of 35 mph. Due to the prevalence of speeding through the construction zone, the Fishers Police Department, Noblesville Police Department, and the Hamilton County Sheriff’s Department have increased patrols along 146th Street. Please be cognizant of the speed limit. It is posted at 35 mph for the safety of our construction crews, as well as local residents exiting their subdivisions through this heavily traveled corridor. Check back for updates as this date approaches.

The contractor will occasionally utilize a lane restriction for the delivery of materials in the work area. These lane restrictions will take place in the left-hand westbound lane of 146th Street.

For additional project information, visit the 146th street and Allisonville rd. Project Page. 

126TH STREET AND SOUTHEASTERN PARKWAY ROUNDABOUT

Effective May 30, 2024 a full road closure will be in effect for 60 days to allow for road reconstruction. A single-lane roundabout at 126th Street and Southeastern Parkway is currently in the design phase to replace the current 126th Street stop condition. The new roundabout will also include a connection for the future development of Hunters Run. The project will rehabilitate or reconstruct the pavement, add curb and gutter with storm sewers, and multi-use paths and/or bicycle lanes. Click here to view a detour route map and for more information visit our Capital Projects Dashboard.

141ST STREET & PROMISE ROAD ROUNDABOUT – HAMILTON COUNTY PROJECT – UPDATE

The City of Noblesville has plans to begin construction on a roundabout at 141st and Promise RD on or after Monday June 17. Once construction begins this closure will last approximately 60 days. The detour route signage will be in place prior to the closure. For your safety, please do not enter the construction zone. There could be open trenches or other obstacles that are unsafe.

For additional project information, visit the 141st Street and Promise Road Roundabout Project Page.

2024 ROAD RESURFACE PROJECT 

The Contractor is continuing work in Sunblest neighborhoodThe week of June 17 road resurface work will take place on 126th street between Olio Road and Thorpe Creek Parkway – traffic will be down to one lane with flaggers on site to direct traffic on Monday June, 17 from 7:30 – 5:30 PM and on Tuesday June 18 from 7:30 to 5:30 PM.

Additonally, the contractor will begin work mid-week on the week of June 17 and has placed door knockers in the Fox Run Neighborhood.

Towards the end of the week of June 17 the contractor will be moving into Hillsborough neighborhood.

We are asking residents to refrain from parking vehicles on the street during active construction operations. Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. For additional project information, view the Capital Project Dashboard here.

View the Road Resurface Overview Map here.

Roadways and neighborhoods are prioritized based on the PASER rating condition of their pavement. You can see a map here.

PROJECTS SOUTH OF 116TH STREET

 

96TH STREET BEAUTIFICATION

The contractor will doing concrete work for the medians on North by Northeast and Kincaid Drive next week . This project will consist of decorative streetlights being installed along 96th Street from North by Northeast Blvd to Cumberland Road. New medians will also be installed along North by Northeast Blvd and Kincaid Blvd with streetlights. Watch out for lane restrictions on North by North East from 9-3pm. For more details visit our Capital Projects Dashboard here.

ROAD CLOSURE – 96TH STREET AND ALLISONVILLE ROAD INTERSECTION

On April 1st,construction began on the 96th St. & Allisonville Rd. Roundabout Project.
This project aims to enhance connectivity along this stretch of the Allisonville Corridor.
The existing Michigan Left intersection was eliminated and transitioned to a two-lane
roundabout adjacent to the new River Place development. This project is slated to be
completed at the end of the year, with minor enhancements completed in the Spring
of 2025. You can view a close up map of what the roundabout will look like after
April 9 here.

Here’s what to expect:

Closures – After April 9, 2024

  • 96th Street is closed from Allisonville Road to Hazel Dell Pkwy.
  • Southbound traffic cannot turn left onto 96th St from Allisonville Rd.
  • Allisonville Rd is open to one lane at 96th Street for North and Southbound traffic.
  • All access to local businesses remains open.
  • See suggested detour maps at 96th & Allisonville Rd Roundabout

We are in constant communication with the County on our traffic signals along 116th Street and working towards accomodating the increased traffic due to this detour. We are aware of the increased volumes due to this project and neighboring ones as well.

ROAD CLOSURE – BRIDGE 187 (106TH STREET OVER MUD CREEK)- HAMILTON COUNTY PROJECT

Please be advised, 106th Street between Cumberland Road and Hamilton Pass has been closed to all thru traffic for a bridge replacement project. The anticipated roadway reopening date is Friday, October 18, 2024.

Local traffic will continue to have access to their homes, while thru traffic is asked to utilize the posted detour route of Cumberland Road, 96th Street, and Mollenkopf Road. For more details visit the Hamilton County page.


HERITAGE PARK BRIDGE – TRAIL CLOSURE 

 

The City of Fishers has partnered with the City of Carmel, Clay Township, Carmel Clay Parks and Recreation, Hamilton County, and Delaware Township to connect Heritage Park at White River and Carmel’s Hazel Landing Park with a bridge over White River. This new amenity will provide enhanced connectivity between the two communities, as well as new recreational opportunities for our residents. To construct this bridge, the contractor will need to restrict access to a portion of Heritage Park’s loop trail that runs adjacent to the river through the woods beginning the week of March 4, click here for an ariel view. During this time, you’ll notice temporary construction fencing going up as we prepare for construction. Beginning the week of March 11, the contractor will work to clear the necessary trees between the park and river. Bridge construction will follow beginning in May. Construction is expected to occur Monday through Saturday beginning at 7 a.m. The bridge is expected to be complete in August 2025.

106TH AND CUMBERLAND
Starting on June 17, there will be lane restrictions at 106th Street and Cumberland Road
while Verizon contractors install underground facilities.  Lane restrictions will be in
place between the hours of 9 am and 3 pm.
BARRETT LAW EAST AND WEST

Parkside/Publishers

Work on Barrett East is substantially complete. See a map here.

Fishers Trade Center 

The contractor will be working on road reconstruction north of 135th st. and south of 141st st. the week of June 17. The construction traffic route is one way, heading north from 135th to 141st st.See a map here.

SIDEWALK IMPROVEMENT PROJECT 

Howard Companies is conducting sidewalk repairs in the Sweet Briar North neighborhood. Restoration work will be underway in Saxony neighborhood. The sidewalk work will consist of removal and replacement of sidewalk panels which pose a toe kick trip hazard. Sidewalk within driveways is not included in the scope of this project.

2022 THOROUGHFARE DRAINAGE IMPROVEMENTS- AREA 3 – INDIANAPOLIS PROJECT

Project Scope: Drainage improvements and structural rehabilitation of Masters Road from 96th Street to 87th Street. The project will be encompassed in two phases.

Masters Road – Phase Two Operations 

  • Flaggers will be in place along Masters Road while road patching and paving work is being completed.
  • Work is expected to be complete by the end of June, weather permitting.
  • Indy DPW will be performing road repair and resurfacing on Masters between 87th and 96th

To view a map of Phase 2 click here,

For more info visit Indianapolis Thoroughfare Drainage Improvements – Area 3  page.