Lots of road construction ongoing in and around Fishers. Also, we aware of more neighborhood street resurfacing and road closures coming for the September 16 Geist Marathon & 5K
Below is the full listing, as provided by the City of Fishers:
============
37Thrives.com. STATE ROAD 37 AND 141ST STREET A pre-construction phase at SR 37 & 141st Street is currently in place. During this phase, 141st Street will be a Right-In-Right-Out (RIRO) traffic configuration. This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Spring 2024. View detour routes here. View how to merge safely onto Northbound SR 37 from 141st Street here and onto Southbound SR 37 from 141st Street here. To navigate the merge, remember:
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit- Use the accel lane to gain speed, not stop
- Use your mirrors and pay attention
- Look for a gap in SR 37 traffic and safely merge
clearpath465.com I-465 & I-69 Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open. The ramp from I-69 North to 82nd Street and the ramp from 82nd Street to I-69 North is currently closed through late 2023. For detour routes and additional project information, visit clearpath465.com
To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit
here. NICKEL PLATE TRAIL The City of Fishers has completed the Fishers portion of the Nickel Plate Trail between Hague Road and 106th Street. Coordination and planning are underway with Indianapolis for the final phase between Hague Road and the crossing of 96th Street.
To learn more about the Nickel Plate Trail, view the Capital Project Dashboard
There are daily lane closures currently on Cumberland Road, just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed.
Phase 2A traffic restrictions are in effect. These restrictions eliminate left turn movements from 146th Street onto Allisonville Road and reopen to two through lanes on eastbound and westbound 146th Street. here. 126TH STREET & PROMISE ROAD On Monday, Sept. 11th and Tuesday, Sept. 12th, westbound 126th Street at Promise Road will have lane restrictions in place between 9 am and 3 pm to allow contractors to repair the railing near the bridge. TANGLEWOOD ROAD RESURFACING Weather permitting, DPW crews will be resurfacing Federal Place in Tanglewood subdivision Wednesday, Sept. 13th through Friday, Sept 15th. Parking restrictions along Federal Place will be in place during this time. You can find affected roadways here.
Utility relocation work is ongoing. Periodic lane closures may be necessary to complete this work. Please watch for flaggers and workers in and around the construction zone. Construction crews are continuing to work on storm sewer installation and roadway grading. Crews have begun working on the widening of the westbound bridge over the White River. The contractor has installed cofferdams and delineating buoys in the White River for pier construction. Please use caution if canoeing or tubing through the work zone. For additional project information, visit the 146th St. & Allisonville Rd. Project PageThere is a sanitary sewer project currently taking place at Metro Airport at 106th Street & Allisonville Road. There are times where lane restrictions may be in place on Allisonville Road. Please use caution in this area.
106TH STREET TRAIL RESTRICTIONS
.
here.
ADA ramp and curb reconstruction has begun in the Harrison Parks and Harrison Lakes as part of the 2023 Resurfacing Project. These areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. Road resurfacing has begun in The Parks at White River and The Bristols. For additional project information and to view detailed exhibits, view the Capital Project Dashboard