Fishers Road Construction for the work week starting Monday, August 21

It will be another busy week for road construction crews in and around the Fishers area.  Be on the alert for several lane closures.

Here is the listing, as provided by the City of Fishers:

===========

STATE ROAD 37 IMPROVEMENT PROJECT

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.comSTATE ROAD 37 AND 141ST STREETA pre-construction phase at SR 37 & 141st Street is currently in place. During this phase, 141st Street will be a Right-In-Right-Out (RIRO) traffic configuration. This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Spring 2024. View detour routes hereView how to merge safely onto Northbound SR 37 from 141st Street here and onto Southbound SR 37 from 141st Street here. To navigate the merge, remember:

  • Use the accel lane to gain speed, not stop
  • Use your mirrors and pay attention
  • Look for a gap in SR 37 traffic and safely merge
CLEAR PATH IMPROVEMENT PROJECT

To learn more about the Clear Path Improvement Project and sign up to receive text and email updates, visit clearpath465.com I-465 & I-69Drivers will see an increase in construction along the I-69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69. Binford Blvd. will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Blvd. will remain open. The ramp from I-69 North to 82nd Street and the ramp from 82nd Street to I-69 North is currently closed through late 2023. For detour routes and additional project information, visit clearpath465.com 

NICKEL PLATE TRAIL

To learn more about the Nickel Plate Trail, view the Capital Project Dashboard here.NICKEL PLATE TRAILThe City of Fishers is working on the completion of the Fishers portion of the Nickel Plate Trail between Hague Road and 106th Street. The installation of pedestrian rail is currently taking place and pedestrian flashers are not operative at this time.

 

PROJECTS NORTH OF 116TH STREET
CUMBERLAND ROAD

There are daily lane closures currently on Cumberland Road, just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed.

146TH STREET & ALLISONVILLE ROAD – HAMILTON COUNTY PROJECT 

Phase 2A traffic restrictions are currently in effect. These restrictions eliminate left turn movements from 146th Street onto Allisonville Road and reopen to two through lanes on eastbound and westbound 146th Street. Utility relocation work is ongoing.  Periodic lane closures may be necessary to complete this work.  Please watch for flaggers and workers in and around the construction zone.  Construction crews are continuing to work on storm sewer installation and roadway grading.  Crews have begun working on the widening of the westbound bridge over the White River.  The contractor has installed cofferdams and delineating buoys in the White River for pier construction.  Please use caution if canoeing or tubing through the work zone.For additional project information, visit the 146th St. & Allisonville Rd. Project Page here.

PROJECTS SOUTH OF 116TH STREET
 
106TH STREET & ALLISONVILLE ROAD

There is a sanitary sewer project currently taking place at Metro Airport at 106th Street & Allisonville Road. There are times where lane restrictions may be in place on Allisonville Road. Please use caution in this area. 

106TH STREET & HOOSIER ROADPrep work prior to the roundabout construction is currently taking place. Work will include tree clearing, utility relocation and storm sewer installation. For additional project information, view the Capital Project Dashboard hereGEIST GREENWAYGeist Greenway is now open between Valley Crossing to 126th Street! Work will resume on the trail south of Valley Crossing Drive on/or after September 1 and remains closed until construction is finished. Construction continues to take place on Florida Road and between Bowline Drive and 104th Street. For general project information, please visit https://playfishers.com/299/Geist-Greenway

106TH STREET

Lane restrictions will be in place on 106th St from Allisonville Rd and Sherbourne Rd on Wednesday, August 23rd to allow crews to replace a sanitary manhole casting.

113th STREET

Lane restrictions will be in place on 113th St. between Olio Rd and Florida Rd on Monday, August 21st for tree trimming operations.

106TH STREET TRAIL RESTRICTIONS

The multipurpose trail on 106th Street from Allisonville Road to Hague Road will be restricted with temporary closures from August 22nd to September 1st for maintenance

.

2023 RESURFACING PROJECT

ADA ramp and curb reconstruction is currently taking place in the Bristols and at the Parks (Harvard, Oxford and Princeton Park) as part of the 2023 Resurfacing Project. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. For additional project information and to view detailed exhibits, view the Capital Project Dashboard here

FALL CREEK ROAD

Rolling lane restrictions will be in place starting Saturday, August 19 through Wednesday, August 23 on Fall Creek Road from 96th Street to Geist Road.  This will allow the contractor to place pavement markings.