As the weather slowly begins to improve, we see more utility relocations and lane restrictions. Be aware of those and other issues from the road construction report for the work week of February 27, as provided by the City of Fishers:
==========
STATE ROAD 37 AND 141ST STREEThere.
A pre-construction phase at SR 37 & 141st Street is currently in place. During this phase, 141st Street will be a Right-In-Right-Out (RIRO) traffic configuration. This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street. The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Summer of 2023. View detour routesPROJECTS ON 116TH STREET
116TH STREET OVER WHITE RIVER BRIDGE
Beginning on or after Monday, February 27, there will be temporary lane closures on 116th Street between Hazel Dell Parkway and Eller Road for bridge joint repairs performed by Hamilton County. One lane will be closed at a time and are expected to occur between 9 a.m. and 2:30 p.m.
PROJECTS NORTH OF 116TH STREET
131ST STREET
During the week of February 27, Comcast will be doing utility work on 131st Street from Howe Road to Promise Road then north on Promise Road to 141st Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.PROJECTS SOUTH OF 116TH STREET
106TH STREET & HOOSIER ROADhere. 106TH STREET & CUMBERLAND ROAD During the week of February 27, Duke Energy will be tree trimming on 106th Street between Cumberland Road and Fall Road. Lane restrictions will be in place between 9 a.m. and 3 p.m. CUMBERLAND ROAD During the week of February 27, Duke Energy will be tree trimming on Cumberland Road between 106th Street and 116th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m. FALL CREEK ROAD Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.
Utility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard