Road Construction Update as of July 15

It’s Friday, it’s the summer season, which means the City of Fishes has a new update on road construction.

The report, as provided by the City of Fishers, is below:

=====

STATE ROAD 37 IMPROVEMENT PROJECT

STATE ROAD 37 AND 146TH STREETAll left-turn lanes are currently restricted on SR 37 and on 146th Street with traffic moved to the interior lanes. Thru traffic and right turns on SR 37 and 146th Street will remain open. Drivers are encouraged to seek alternate routes for all left turn access. View an alternate route map here.  On Tuesday, July 19 and Wednesday, July 20 there will be single lane restrictions on SR 37 to put traffic onto the newly constructed SR 37 pavement. Access to 146th Street will still remain the same with no left turns. STATE ROAD 37 AND 131ST/135TH STREET135th Street, east of SR 37, is currently closed as work progresses on the project. This closure will be in place until early July. SR 37 will remain open both northbound and southbound and allow right in/right out access at 131st Street. View the detour map here.On Wednesday, July 20 and Thursday, July 21 between 2 a.m. and 7 a.m. there will be single lane restrictions on SR 37 to mill and resurface the median lane between 126th Street and 131st Street. Please drive with caution through this area. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

PROJECTS NORTH OF 116TH STREET 
TECHNOLOGY DRIVE (NORTHEAST COMMERCE PARK)

The inside lane of the Technology Drive is currently closed to traffic to allow for construction of new pavement in the inside lane.  One-way traffic will be in place in the outside lane as shown here.  Access to all businesses will be maintained during the construction.

SOUTHEASTERN PKY. & CYNTHEANNE ROAD

The intersection at Southeastern Pky. & Cyntheanne Road is currently closed for roundabout construction and is anticipated to reopen by the end of July. View the detour map here.  Schoolhouse 7 Café will remain open for business during construction. View how to access their business here

COMMERCIAL DRIVE

On Monday, July 18, there will be lane restrictions on Commercial Drive, just north of 116th Street, between 6 a.m. and 8 a.m. for utility work. 

CUMBERLAND ROAD

During the week of July 18, road resurfacing work will be taking place on Cumberland Road between 126th Street and 131st Street. Flaggers will be in place. 

PROJECTS SOUTH OF 116TH STREET 
OLIO ROAD

Olio Road between Geist Reservoir and Haven Cove Lane, the first road south of the Geist Reservoir Bridge, may have daily lane restrictions for the reconfiguration and installation of access to Geist Waterfront Park and the Marina. These lane restrictions will occur between the hours of 9 a.m. and 4 p.m., Monday thru Friday. The estimated completion date is August 1, 2022.  

PROJECTS ON 116TH STREET 

The outside eastbound lane of 116th Street, just after the Nickel Plate Trail bridge, will be restricted between 9 a.m. and 3 p.m. through Friday, July 22 for work on the FIB building. Arrow boards will be in place.Comcast will have daily lane restrictions in place on westbound 116th Street between Cameron Drive and Allisonville Road and northbound Allisonville Road between 116th Street to the Kroger signal for overhead work. Restrictions will be in place between 9 a.m. and 3 p.m.

 

2022 RESURFACING PROJECT

ADA ramp and curb reconstruction has started taking place in Delaware Point and Overlook at Beaver Ridge as part of the 2022 Resurfacing Project. Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.