It’s Friday, which means another update on local road construction.
Along with the previously announced reopening of 116th Street at the Nickel Plagte Trail, watch for lane restriction on State Road 37 & I-69.
Here is the full listing, as provided by the City of Fishers:
=======
STATE ROAD 37 IMPROVEMENT PROJECT
STATE ROAD 37 AND 146TH STREET STATE ROAD 37 AND 131ST / 135TH STREETS The Northbound SR 37 right turn lane onto 135th Street is currently closed from 131st Street to approximately halfway to 135th Street for Phase 1 construction. This portion of the dedicated turn lane will not reopen to regular capacity until the interchange is complete. Please drive with caution through this area. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com. |
|||||
NICKEL PLATE TUNNEL PROJECT
116TH STREET AT THE NICKEL PLATE TRAIL
Even with the nearly record rainfalls over the last 45 days, our Engineering team and contractors have been hard at work building the new Nickel Plate Trail pedestrian tunnel beneath 116th Street. Ahead of schedule, we will reopen 116th Street between Municipal Drive and Maple Street to a single lane of traffic in each direction beginning Saturday, July 17. Additional lanes will remain closed until August 1 while we put the finishing touches on this project. Please be mindful that construction is still occurring on 116th Street over the next few weeks, and please use caution in the area. In using 116th for thru travel and not local business access, we suggest continuing to seek an alternate route until construction is completed. We appreciate your patience as we continue to improve our city. Learn more about the Nickel Plate Trail project here: https://www.playfishers.com/284/Nickel-Plate-Trail PROJECTS NORTH OF 116TH STREET
SR 37 & I-69
Beginning on Friday, July 23 at 9:00 p.m., one lane in each direction on the SR 37 Northbound and Southbound bridges over I-69 will be restricted for placing a bridge deck overlay. All lanes are anticipated to open by Monday, July 26 at 6:00 a.m.
2021 RESURFACING PROJECT
ROYALWOOD
Milling and resurfacing work is currently taking taking place in Royalwood. Please be aware of street signage for street parking restrictions. Flaggers will be in place to direct traffic.
CANAL PLACE
Milling and resurfacing work is currently taking place in Canal Place. Please be aware of street signage for street parking restrictions. Flaggers will be in place to direct traffic.
DPW PROJECTS
CRACK SEALING
Over the next two weeks, as weather allows, DPW will be crack sealing in the following areas: Kincaid Drive, USA Parkway, Ikea Way, Roberts Drive, Burberry, Bluestone and Whitmire Glen. Lane restrictions and flaggers will be in place.
DIAMOND GRINDING
DPW and their contractor will be diamond grinding both Northbound and Southbound lanes of Allisonville Road between 116th Street to Orchard Blvd. The work will require rolling single lane restrictions and reduced lane width. The work will take place between 4:30 a.m. and 4:30 p.m. Monday through Friday. STRIP PATCHING
DPW will be strip patching Westbound 131st Street east of Promise Road, Westbound 106th Street between Allisonville Road and Eller Road, Gatwick View Drive and Belle Plaine Blvd. Lane restrictions and flaggers will be in place. |