There is plenty of road construction in Fishers, some continuing and other smaller projects underway.
Here is the latest rundown, as provided by the City of Fishers:
=========================
STATE ROAD 37 IMPROVEMENT PROJECT
STATE ROAD 37 AND 146TH STREET STATE ROAD 37 AND 131ST / 135TH STREETS The Northbound SR 37 right turn lane onto 135th Street is currently closed from 131st Street to approximately halfway to 135th Street for Phase 1 construction. This portion of the dedicated turn lane will not reopen to regular capacity until the interchange is complete. Please drive with caution through this area. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com. |
|||||
NICKEL PLATE TUNNEL PROJECT
116TH STREET AT THE NICKEL PLATE TRAIL
The City of Fishers started construction on the Nickel Plate Trail pedestrian tunnel beneath 116th Street on Tuesday, June 1. The closure is anticipated to last 60 days. During the construction, 116th Street will be closed from east of Municipal Drive to west of Maple Street. All local business and public parking access will remain open. 106th Street will serve as the detour route, with the detour beginning at Hague Road for eastbound thru traffic and Lantern Road for the westbound thru traffic. Portions of the Nickel Plate Trail are now open, including the paved portion from 131st Street to North Street, and from South Street to 106th Street. The 116th Street tunnel will complete the trail connection through downtown Fishers, joining South Street and North Street, and establishing a full connection from 131st Street to 106th Street. While the tunnel is under construction, a pedestrian detour route will provide access through downtown between the north and south sections of the trail. View the pedestrian detour map here. To learn more about the project, view construction images and project renderings, and find detour maps, visit https://www.playfishers.com/284/Nickel-Plate-Trail 2021 RESURFACING PROJECT
SOUTH AVALON
Milling and resurfacing work is currently taking place in South Avalon. Please be aware of street signage for street parking restrictions. Flaggers will be in place to direct traffic.
ROYALWOOD
Milling and resurfacing work is currently taking taking place in Royalwood. Please be aware of street signage for street parking restrictions. Flaggers will be in place to direct traffic.
CANAL PLACE
Beginning the week of July 12, milling and resurfacing work will begin in Canal Place. Please be aware of street signage for street parking restrictions. Flaggers will be in place to direct traffic.
DPW PROJECTS
CRACK SEALING
Over the next two weeks, as weather allows, DPW will be crack sealing in the following areas: Kincaid Drive, USA Parkway, Ikea Way, Roberts Drive, Burberry, Bluestone and Whitmire Glen. Lane restrictions and flaggers will be in place.
DIAMOND GRINDING
Beginning the week of July 12, DPW and their contractor will be diamond grinding both Northbound and Southbound lanes of Allisonville Road between 116th Street to Orchard Blvd. The work will require rolling single lane restrictions and reduced lane width. The work will take place between 4:30 a.m. and 4:30 p.m. Monday through Friday. STRIP PATCHING
Beginning the week of July 12, DPW will be strip patching Westbound 131st Street east of Promise Road, Westbound 106th Street between Allisonville Road and Eller Road, Gatwick View Drive and Belle Plaine Blvd. Lane restrictions and flaggers will be in place. |