The latest road construction update

The weather may not be warm enough for the the satisfaction of many people in and around Fishers, but that is not stopping road crews as construction continues in and around the city.

Here is the latest road construction update, as provided by the City of Fishers:

===========

STATE ROAD 37 IMPROVEMENT PROJECT

STATE ROAD 37 AND 146TH STREET
All left-turn lanes are currently restricted on SR 37 and on 146th Street with traffic moved to the interior lanes. Thru traffic and right turns on SR 37 and 146th Street will remain open. Drivers are encouraged to seek alternate routes for all left turn access. View an alternate route map here.

Northbound and Southbound SR 37 is currently restricted to one lane in each direction, North of 146th Street. This restriction will be in place for approximately 2-3 weeks, as work progresses at this interchange.

There is currently a single lane closure for Northbound Herriman Blvd. between 146th Street and the Circle K/Shell gas station driveway and is anticipated to reopen in May.

STATE ROAD 37 AND 131ST / 135TH STREETS
The westside of 131st Street at SR 37 is currently closed as work progresses on the interchange. SR 37 will remain open both north and southbound. SR 37 southbound left and right turns onto 131st Street will be restricted. Left turns onto SR 37 will also be restricted for westbound traffic on 131st Street from the east approach. View the detour map here.

The Northbound SR 37 right turn lane onto 135th Street is currently closed from 131st Street to approximately halfway to 135th Street for Phase 1 construction. This portion of the dedicated turn lane will not reopen to regular capacity until the interchange is complete.

Please drive with caution through this area. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

NICKEL PLATE TUNNEL PROJECT

 

116TH STREET AT THE NICKEL PLATE TRAIL

The City of Fishers will begin construction on the Nickel Plate Trail pedestrian tunnel beneath 116th Street on or after June 1. 116th Street will be closed from east of Municipal Drive to west of Maple Street during the construction. 106th Street will serve as the detour route, with the detour beginning at Hague Road for eastbound thru traffic and Lantern Road for the westbound thru traffic. The closure is anticipated to last 60 days. All local business and public parking access will remain open.

Daily lane restrictions are currently in place on 116th Street between 9 a.m. to 3 p.m. on 116th Street near the Nickel Plate Trail for utility relocation prior to the closure.

Learn more about the Nickel Plate Trail project at https://www.playfishers.com/284/Nickel-Plate-Trail

PROJECTS ON 116TH STREET 

116TH STREET

Beginning on Tuesday, May 11, there will be single lane restrictions on 116th Street and the I-69 bridge approach between 9 p.m. and 6 a.m. as DPW makes repairs. This work is anticipated to be completed by 6 a.m. on Friday, May 14.

On Wednesday, May 12, the Exit 5 Pkwy. northbound thru lane, just North of 116th Street will be closed, and thru traffic will be pushed into the northbound left turn lane. The 116th Street outer eastbound to northbound Exit 5 Pkwy. will also be closed as DPW replaces streetlights. This work will take approximately 3 hours.

Beginning on Thursday, May 13, there will be single lane restriction on westbound 116th Street between Brooks School Road to Hoosier Road between 6 a.m. and 4:30 p.m. as DPW completes joint repairs. This work is anticipated to be completed on Friday, May 14.

On Friday, May 14, there will be a short lane restriction on westbound 116th Street at Holland Drive for overhead utility work. An arrow board will be in place to help direct traffic.

PROJECTS NORTH OF 116TH STREET 
ALLISONVILLE ROAD

Beginning on Monday, May 10, there will be temporary lane restrictions on Allisonville Road near 146th Street for survey work. Flaggers will be in place to direct traffic.

PROJECTS SOUTH OF 116TH STREET 
SOUTH STREET, MOORE STREET & ROYAL DRIVE 

There are lane restrictions currently on South Street and Moore Street as crews work on storm structures. The contractor will also be working on the storm sewer outlet structure on Royal Drive.

ALLISONVILLE ROAD

Beginning on Monday, May 10 there will be single lane restrictions on Allisonville Road between Easy Street and 106th Street between 6 a.m. and 4:30 p.m. as DPW completes joint repairs. This work is anticipated to be completed on Tuesday, May 11.

106TH STREET

There are lane restrictions currently in place for east and west bound traffic on 106th Street at Hague Road. Through lanes will be restricted and traffic will use the left turn lanes as through lanes. Left turn access onto Hague Road will remain open. Advanced warning signs will be in place. These restrictions are anticipated to be in place until mid-May for bypass pumping for improvements to the Hague Road Lift Station.

ADMIRALS POINTE DRIVE

Indianapolis DPW currently has Admirals Pointe Drive closed through midsummer 2021 to replace the timber bridge over Geist and the north fork of Dry Branch. The detour will consist of Old Stone Dr. East to Carroll Rd. / 700 W., South to E. 79th St., West to Oaklandon Rd.

2021 RESURFACING PROJECT


ADA ramp and curb reconstruction has started as part of the 2021 Resurfacing Project. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.

NORTHFIELD ESTATES & EASY STREET
Milling and resurfacing work is currently taking place in Northfield Estates and on Easy Street, from Allisonville Road to Autumn Frost Circle Lane. Please be aware of street signage for street parking restrictions. Flaggers will be in placeWOODBERRY & CUMBERLAND PLACE
Beginning the week of May 10, milling and resurfacing work will begin taking place in Woodberry and Cumberland Place. Please be aware of street signage for street parking restrictions. Flaggers will be in place to direct traffic.

SOUTH AVALON
ADA ramp work is currently taking place in South Avalon and is anticipated to be completed in May.


CRACK SEALING – DPW

Over the next two weeks, as weather allows, DPW will be crack sealing in the following areas: The Haven, Timber Springs, Berkley Grove, Berkley Ridge, Roxbury, The Pines, USA Parkway, 106th Street (Eller Road to Lantern Road) and Eller Road (106th Street to Allisonville Road). Lane restrictions and flaggers will be in place.

 

CAPITAL PROJECT DASHBOARD
A Capital Project Dashboard is now available on Drive Fishers. The dashboard was created to offer an interactive mapping and data tool, which allow users the ability to filter data and find the most current details on Engineering capital projects. View the Capital Project Dashboard here