Road Construction Update

It’s time for the weekly road construction update from the City of Fishers.

Below is the full listing, as provided by the city:

================

STATE ROAD 37 IMPROVEMENT PROJECT

STATE ROAD 37 AND 146TH STREET
All left-turn lanes are currently restricted on SR 37 and on 146th Street with traffic moved to the interior lanes. Thru traffic and right turns on SR 37 and 146th Street will remain open. Drivers are encouraged to seek alternate routes for all left turn access. View an alternate route map here

Northbound and Southbound SR 37 is currently restricted to one lane in each direction, North of 146th Street. This restriction will be in place for approximately 2-3 weeks, as work progresses at this interchange.

There is currently a single lane closure for Northbound Herriman Blvd. between 146th Street and the Circle K/Shell gas station driveway and is anticipated to reopen in May.

STATE ROAD 37 AND 131ST / 135TH STREETS
The westside of 131st Street at SR 37 is currently closed as work progresses on the interchange. SR 37 will remain open both north and southbound. SR 37 southbound left and right turns onto 131st Street will be restricted. Left turns onto SR 37 will also be restricted for westbound traffic on 131st Street from the east approach. View the detour map here.

The Northbound SR 37 right turn lane onto 135th Street is currently closed from 131st Street to approximately halfway to 135th Street for Phase 1 construction. This portion of the dedicated turn lane will not reopen to regular capacity until the interchange is complete.

Please drive with caution through this area. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

NICKEL PLATE TUNNEL PROJECT


116TH STREET AT THE NICKEL PLATE TRAIL

The City of Fishers will begin construction on the Nickel Plate Trail pedestrian tunnel beneath 116th Street on or after June 1. 116th Street will be closed from east of Municipal Drive to west of Maple Street during the construction. 106th Street will serve as the detour route, with the detour beginning at Hague Road for eastbound thru traffic and Lantern Road for the westbound thru traffic. The closure is anticipated to last 60 days. All local business and public parking access will remain open.

Lane restrictions are currently in place on 116th Street for utility relocation prior to the closure. The outside, westbound lane is closed until Thursday, May 6. Beginning May 6, lane restrictions will be in effect from 9 a.m. to 3 p.m. daily through the June 1 closure.

Learn more about the Nickel Plate Trail project at https://www.playfishers.com/284/Nickel-Plate-Trail

PROJECTS NORTH OF 116TH STREET 
141ST STREET

Beginning on Monday, May 3, DPW will be performing full depth patching on 141st Street between SR 37 and Harrison Parkway. Work is anticipated to be completed on Wednesday, May 5.

PROJECTS SOUTH OF 116TH STREET 
SOUTH STREET, MOORE STREET & ROYAL DRIVE 

During the week of May 3, there will be lane restrictions on South Street and Moore Street as crews work on storm structures. The contractor will also be working on the storm sewer outlet structure on Royal Drive.

ALLISONVILLE ROAD

Beginning on Tuesday, May 4, there will be single lane restrictions on Allisonville Road between 106th Street and Easy Street between 6 a.m. and 4:30 p.m. as DPW completes joint repairs. This work is anticipated to be completed on Friday, May 7.

96TH STREET & I-69

During the week of May 3, there will be nighttime signal work occurring at the 96th Street & I-69 interchange.

Overnight work will begin on Saturday, May 1 at approximately 7 p.m. to install landscaping in the 96th Street median of I-69 before Hague Road. The inside lane on 96th Street will be partially blocked and is anticipated to reopen by 7 a.m. on Sunday, May 2.

CHARLESTON CROSSING

On Thursday, May 6 and Friday, May 7, DPW will continue asphalt patching in Charleston Crossing.

106TH STREET

There are lane restrictions currently in place for east and west bound traffic on 106th Street at Hague Road. Through lanes will be restricted and traffic will use the left turn lanes as through lanes. Left turn access onto Hague Road will remain open. Advanced warning signs will be in place. These restrictions are anticipated to be in place until mid-May for bypass pumping for improvements to the Hague Road Lift Station.

ADMIRALS POINTE DRIVE

Indianapolis DPW currently has Admirals Pointe Drive closed through midsummer 2021 to replace the timber bridge over Geist and the north fork of Dry Branch. The detour will consist of Old Stone Dr. East to Carroll Rd. / 700 W., South to E. 79th St., West to Oaklandon Rd.

2021 RESURFACING PROJECT


ADA ramp and curb reconstruction has started as part of the 2021 Resurfacing Project. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.

NORTHFIELD ESTATES & EASY STREET
Beginning the week of May 3, milling and resurfacing work will begin taking place in Northfield Estates and on Easy Street, from Allisonville Road to Autumn Frost Circle Lane. Please be aware of street signage for street parking restrictions. Flaggers will be in place

SAXONY
ADA ramp work is currently taking place in Saxony and is anticipated to be completed in May.

SOUTH AVALON
ADA ramp work is currently taking place in South Avalon and is anticipated to be completed in May.


CRACK SEALING – DPW

Over the next two weeks, as weather allows, DPW will be crack sealing in the following areas: The Haven, Berkley Grove, Berkley Ridge, Roxbury, The Pines, USA Parkway, 106th Street (Eller Road to Lantern Road) and Eller Road (106th Street to Allisonville Road). Lane restrictions and flaggers will be in place.