The road construction gets a little longer the deeper we get into the season.
Below is the latest update from the City of Fishers, covering the work week starting Monday, May 13th:
===========
MUNICIPAL DRIVE
The northwest side of Municipal Drive is closed for storm sewer work for the new Flexware Innovation and Fishers Ellipse, LLC. buildings. The closure is on the north side of Municipal Drive from the Nickel Plate District Amphitheater west to the Fire Station parking lot. Motorists can still access Municipal Drive from Lantern Road. The closure is expected to last for another 2 weeks.
STATE ROAD 37
Drainage work for SR37 is in progress. Construction vehicles will be using the construction entrance on Lantern Road, between 126th Street and 131st Street, and may cause some short delays.
116TH STREET
There is a temporary lane restriction on eastbound 116th Street between Municipal Drive and Commercial through Friday, May 17. The restriction will be in effect between 8:30 a.m. and 3:30 p.m.
136th STREET & CYNTHEANNE ROAD
Temporary lane restrictions are in effect between 9 a.m. and 3 p.m. near and at the intersection of 136th Street and Cyntheanne Road. Restrictions are due to utility work for roundabout construction. For more information on this project, view the Fact Sheet.
ALLISONVILLE ROAD
126th Street at Allisonville Road closed on Monday, April 22 for approximately 30 days. Detour routes are down 131st Street and 116th Street to Lantern Road. Homes along 126th Street can be accessed from Lantern Road. Allisonville Road will remain open. For more information on this project, view the Fact Sheet.
Southbound and northbound traffic on Allisonville Road has moved onto the newly constructed pavement as part of Phase 3 of the project. The posted speed limit remains 30 mph.
126TH STREET
Work has begun on intersection improvements for 126th Street and Parkside Drive. View the Fact Sheet to learn more about this project.
Traffic will be switched this week to the south. There will still be one lane of traffic in each direction while construction is being completed.
96TH STREET
Utility relocation is beginning on 96th Street as part of the road widening project, resulting in periodic lane restrictions over the coming months. For more information about the 96th Street road widening project, view the Fact Sheet.
(While this list encompasses numerous project updates, it does not list all DPW projects throughout the city. The most recent projects are detailed, however please keep in mind that all construction activities are weather permitting. We appreciate motorists’ patience and caution while driving through construction sites)