Fishers Road Construction Listing, and Spark!Fishers Closures

If you are wondering how traffic will be impacted by the June 30th Spark Fishers Festival in the downtown area of Fishers, there is information about that in this week’s road construction report.  Also, look for lane restrictions on part of 141st start beginning in the coming week.

Below is the complete listing for the work week starting July 2nd, as provided by the City of Fishers:

==========================

SPARK!FISHERS FESTIVAL

The inaugural Spark!Fishers community festival is Saturday, June 30. Setup will begin at 8 a.m. on Friday, June 29. Lanes will be restricted for setup on the south side of Municipal Complex from North Street to Fishers Center Drive, and on Maple Street from North Street to 116th Street. Street parking and surface lots around the Municipal Complex will be restricted beginning at 5 a.m. on June 29 and will reopen at 11:59 p.m. on Saturday, June 30. For parking information, please visit sparkfishers.com.

On June 30, restrictions and closures will be in effect in the following locations:
Full street closures beginning at 5 a.m.

  • 116th Street between Municipal Drive and Lantern Road (reopens at 9 a.m.)
  • Entire Municipal Complex (reopens at 11:59 p.m.)
  • Maple from North Street to 116th Street (reopens at 11:59 p.m.)
  • North Street from Lantern to Municipal (reopens at 11:59 p.m.)

Full street closures beginning at 7 a.m.

  • 116th Street between Holland Drive and Municipal Drive (reopens at 9 a.m.)
  • Lantern Road between 116th Street and 126th Street (reopens at 9 a.m.)
  • 126th Street between Lantern Road and Saksons Blvd (reopens at 9 a.m.)
  • Saksons Blvd/Holland Drive between 126th Street and 116th Street (reopens at 9 a.m.)

Lane restrictions beginning at 5 p.m.

  • Technology Drive (reopens at 9 p.m.)

Full street closures beginning at 6 p.m.

  • Lantern Road between 116th Street and Sunblest Blvd (reopens at 10 p.m.)
  • Holland Park Drive to Ellipse Parkway to Sunblest Blvd. (reopens at 10 p.m.)
  • 116th Street from Lantern Road to Holland Park Drive (reopens at 10:30 p.m.)

141ST STREET   

Beginning July 2, there will be lane restrictions along 141st Street between Allisonville Road and SR37 for resurfacing work. Flaggers will be in place to direct traffic.

ALLISONVILLE ROAD

Allisonville Road construction is in full swing. Traffic has been shifted to the east to allow for widening on the west side. Restrictions may be in place between 8 a.m. and 4 p.m. and flaggers will be on site directing traffic, as necessary. Through September, all southbound left turns from Allisonville Road onto 126th Street will be prohibited.

This will be an active construction site with reduced speed limits. For more info on this project, view the Fact Sheet.

116TH STREET

Eastbound 116th Street from Allisonville Road to Fishers Pointe Blvd. is reduced to one lane between 9 a.m. and 3 p.m. for resurfacing of the path on the south side of the roadway. Westbound 116th Street from Fishers Pointe Blvd. to Hague Road will be reduced to one lane between 9 a.m. and 3 p.m. for work on the street lights on the north side of the roadway.

There will be temporary lane restrictions on Eller Road south of 106th Street for pavement restoration. Flaggers will be in place to direct traffic.

116TH STREET & BROOKS SCHOOL ROAD

There will be lane restrictions on 116th Street and Brooks School Road this week for resurface work on both streets.

131ST STREET   

The intersection of 131st and Cumberland Road is currently closed for 45 days to construct a new roundabout. See the Detour Map.

Expect lane restrictions, weather permitting, along 131st Street between Allisonville Road and Lantern Road for the construction of the Conner Trail from Conner Prairie to the Municipal Complex. Lane restrictions will also take place on Lantern Road between 131st Street and Municipal Drive.

NICKEL PLATE DISTRICT 

For the Tuesday evening concert on Central Green, Municipal Drive in front of City Hall will be closed for stage construction beginning at noon. Also beginning at noon, North Street and Municipal Drive will become a right turn only, and Fishers Center Drive and Municipal Drive will become a left turn only. Beginning at 5 p.m., there will be road closures on Municipal Drive at 116th Street, on Municipal Drive at Fishers Center Drive (vehicles will still be able to turn left), and on Municipal Drive at North Street (vehicles will still be able to turn right). Roads will reopen at midnight. Street parking on Municipal Drive will be restricted from 2 p.m. until midnight. Guests can access the event from Fishers Center Drive, Municipal Drive (north), and North Street. Parking is available at The Switch garage, accessed from North Street.

The Board of Works recently passed an ordinance for no parking in the Nickel Plate District between the hours of 3 a.m. and 6 a.m. See the Parking Restrictions Map for more information.

BROOKS SCHOOL ROAD  

Brooks School Road will be closed for 30 days beginning on or after July 5, south of 116th Street between Desert Glen Drive and Club Point Drive. The detour route is Hoosier Road and Fall Creek Road. View the Detour Map.

Brooks School Road is closed between 126th Street and 136th Street to build a sidewalk to the east side of the bridge over I-69. Detours via 136th Street, Promise Road, and 126th Street to get around the closure. The road will reopen in early August. Questions can be directed here.

136TH STREET

136th Street is closed between Southeastern Parkway and Prairie Baptist Road for the construction of a new roundabout. See the Detour Map.

106TH STREET   

106th Street is closed to through traffic from Eller Road to Allisonville Road and from Allisonville Road to Hague Road for the 106th Street Infrastructure Project. Closures for through traffic will also take place from Hague Road to the Crosspoint Boulevard/Lantern Road roundabout. For more info on this project, view the Fact Sheet.

I-69   

As part of a $92 million design-build contract, Milestone has added a third lane in each direction to the median, repaired and resurfaced existing pavement, and rehabilitated bridges and drainage structures on 15 miles of I-69 in Hamilton and Madison counties. Construction of an additional auxiliary lane between the 116th Street entrance ramp to I-69 South and the I-69 South Exit 204 ramp to 106th Street will continue through next spring.

I-69 South will be temporarily reduced to two lanes to allow space for the State Road 37 and 116th Street entrance ramps to safely merge while construction continues on the southbound auxiliary lane between the 116th Street and 106th Street ramps.

Questions about this project should be directed to INDOT via email or at 1-855-463-6848.

STATE ROAD 37

A public meeting was held on Tuesday, May 15at the Delaware Township Trustee Office. The meeting presentation and updated information is available on the project’s new website. The State Road 37 improvement project is a $124 million joint project between Fishers, Hamilton County, Noblesville, and INDOT. Questions or concerns may be directed to SR37@rqaw.com. 

OUTSIDE OF FISHERS   

The City of Carmel has closed 116th Street between Towne Road and Ditch Road, and between Clay Center Road and Spring Mill Road, until August 8.

While this list encompasses numerous project updates, it does not list all DPW projects throughout the city. The most recent projects are detailed, however please keep in mind that all construction activities are weather permitting. We appreciate motorists’ patience and caution while driving through construction sites.