Fishers Road Construction – Work Week Beginning Monday, November 6th

The listing of road construction projects in and around Fishers is an update on a number of ongoing work.  Below is the listing for the work week starting Monday, Nobember 6th, as provided by the City of Fishers:

==============================

116TH STREET GRAND OPENINGS
With the recent openings of IKEA, Top Golf and Portillo’s, please expect delays along the 116th Street corridor. Residents and visitors are encouraged to visit www.Fishers.in.us/Openings for directional maps and suggestions on how to navigate the area. The Fishers IN and Drive Fishers Twitter accounts will both be updated in an ongoing fashion should any immediate updates be shared.

146TH STREET
Westbound 146th Street east of Allisonville Road in the right turn lane to northbound Allisonville Road will be restricted for test borings, as well as the right eastbound lane of 146th Street west of Allisonville Road. Traffic control will be in place from 9 a.m. – 3 p.m. for the next 7 days. Please contact Hamilton County Highway Department at 317-773-7770 with any questions.

141ST STREET
Lane shifts will occur on 141st Street west of SR37 to allow for the construction of a turn lane along the north side of the roadway. Barrels and cones will be in place to direct traffic through the shift.

116TH STREET
Periodic lane restrictions will occur on 116th Street east of Allisonville Road as the contractor repairs concrete curbs and ramps and begins resurfacing work on the roadway. Restrictions will be in place between 9 a.m. – 3 p.m. Please note that overnight work will occur while traffic volumes are reduced. The City greatly appreciates residents’ patience with construction noise.

I-69
Improvements are currently underway to rehabilitate existing bridges, pavement and drainage structures along the 15-mile stretch of interstate. Two lanes of traffic in each direction of I-69 are currently shifted to accommodate construction of the additional travel lanes. Signs direct large trucks to use the left lane while traffic is shifted toward the right shoulder through the work zone. The speed limit is reduced to 60 mph and further reduced to 50 mph when workers are present. I-69 is expected to open to three lanes in each direction between State Road 37 and State Road 38 before the end of this year. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

STATE ROAD 37
Geotechnical drilling began along the State Road 37 corridor in May as part of the final design phase of State Road 37 Improvement Project. Lane and shoulder restrictions will be active through November as crews finish drilling. The State Road 37 improvement project is a $124 million joint project between Fishers, Hamilton County, Noblesville and INDOT. Questions or concerns may be directed to drivefishers@fishers.in.us.

OUTSIDE OF FISHERS
Cyntheanne Road between 146th Street and 156th Street will be closed until December 1, 2017 to replace the bridge over Keiser Drain. Please contact Hamilton County Highway Department at 317-773-7770 with any questions.

While this list encompasses numerous project updates, it does not list all DPW projects throughout the city. The most recent projects are detailed, however please keep in mind that all construction activities are weather permitting. We appreciate motorists’ patience and caution while driving through construction sites.