Be Prepared – I-69 Exit 210 Interchange Big Change Coming May 16, 17

We knew it was coming, it is now upon us – the Double-Crossover Diamond traffic pattern is coming May 17th.  In order for that to happen,   Southeastern Parkway/Campus Parkway over I-69 will close at 9pm May 16th, reopening at 6am May 17th.  There will also be some overnight lane restrictions along I-69.  This will be a big change, so be prepared.

Also be aware of lane restrictions along 116th Street between the Interstate and Cumberland Road will be a regular thing all summer long as improvements are made to that area of road.

If that isn’t enough, look for lane restriction along State Road 37 through June 30th as preparations continue to the big rebuild on that stretch of highway.

There are other items to look for during the work week beginning May 15th.  Below is the full listing, as provided by the City of Fishers:

===========================

 

116TH STREET

There will be lane restrictions on 116th Street between I-69 and Cumberland Road throughout the summer in order for the contractor to make improvements to 116th Street.

106TH STREET

There will be lane restrictions on 106th Street from Eller Road to I-69 the week of May 15 while a contractor locates utilities under the roadway. There will be arrow boards and flaggers in place while work is being performed between 9am and 3pm. There will be lane restrictions on Allisonville Road as well while the contractor works in this intersection.

GEIST ROAD

Geist Road between 106th Street and 111th Street will have possible lane restrictions while contractors perform shoulder work along the west side of Geist Road.

USA PARKWAY

There will be periodic restrictions on USA Parkway while crews construct turn lanes for IKEA.

I-69 AND CAMPUS PARKWAY

Weather permitting, INDOT will close Southeastern Parkway/Campus Parkway over I-69 Tuesday night (5/16) starting at 9pm and will reopen by 6am Wednesday morning.

The Campus Parkway interchange at Interstate 69 Exit 210 will be shifted into a double-crossover diamond traffic pattern starting on or after May 17. Shifting traffic into the double-crossover diamond pattern is intended to improve traffic flow during the remainder of construction of the permanent interchange improvements. For more information about the project, please visit http://www.in.gov/indot/3441.htm.

Milestone Contractors has begun mobilizing cranes and other equipment and setting a temporary concrete barrier wall along I-69 at Campus Parkway Exit 210. Work will require alternating lane closures on northbound and southbound I-69 between 9pm and 6pm Lane closures may recur each night through the end of the week depending on weather and progress. Questions about this project should be directed to INDOT at eastcentralin@indot.in.gov or 1-855-463-6848.

106TH AND CUMBERLAND ROAD ROUNDABOUT

There will be possible lane restrictions around the roundabout while the contractor finishes up work.

126TH STREET

There will be periodic lane restrictions between 9am and 3pm on 126th Street between Allisonville Road and Lantern Road while the contractor installs passing blisters near Reserve at Lantern. Flaggers will be on site to direct traffic during the restrictions.

ALLISONVILLE ROAD

There will be lane restrictions on northbound and southbound Allisonville Road from 126th Street to 131st Street between 9am and 3pm all week.  There will be flaggers and barrels onsite to help direct traffic.  Please drive with caution.

STATE ROAD 37

Starting May 1, geotechnical drilling will begin along the State Road 37 corridor as part of the final design phase of State Road 37 Improvement Project. Lane and shoulder restrictions will be active through the June 30.

Motorists will see staked locations along the corridor starting with the 141st Street intersection. The geotechnical drilling will cause lane restrictions from 131st Street through 146th Street through June 30. Southbound restrictions will not begin until 9am daily and northbound restrictions will be done daily before 4pm to allow for maximum traffic flow during peak hours.

State Road 37 turn lanes will not be affected during lane closures and crews will maintain a minimum of one through-lane at all times.

The SR37 improvement project is a $124 Million joint project between Fishers, Hamilton Co, Noblesville, and INDOT. Questions or concerns may be directed to drivefishers@fishers.in.us.