Fishers Road Construction Schedule – Work Week Beginning July 13th

We are in the heart of the road construction season and the work schedule is not slowing down in Fishers.  Below is a listing from the city with all the projects set to be done during the work week beginning Monday, July 13th…

=========================================

Burberry Place

Concrete repair work will continue taking place in Burberry Place through the week.


Eller Road Closure

Eller Road between 106th Street and 116th Street will be closed for the replacement of the bridge over Cheeney Creek. The road will be closed to traffic through early August. During this time a detour will be available along 106th Street, Allisonville Road and 116th Street. Fishers Heritage Park will be accessible during construction, and local traffic will be able to proceed south on Eller Road as far as Round Up Trail and White Horse Lane. This is a Hamilton County Highway Department project and questions can be directed to their department at (317) 773-7770.

Georgia Road

Restrictions continue the week of July 13th on 104th Street between Georgia Road and Florida Road to allow for shoulder work. There will be flaggers onsite during construction.

Lantern and Commercial

Lanes may be reduced as work on the intersection and railroad continues.  Please travel with caution in the area.

North Street

Lane restrictions will be in place until August 6th for North Street between Municipal Drive and the railroad tracks. Flaggers will be in place.

Promise Road

Utility work along Promise between 131 Street and 141 Street will continue along with periodic lane restrictions. Flaggers will be onsite.

96th Street Power Lines

Power line transfers and old pole removal will continue the week of July 13th along 96th Street going east from Cyntheanne Road to Fortville city limits. This project is ongoing and updates will be posted as they become available. Flaggers will be onsite to help direct traffic.

131st Street Construction

Road and shoulder construction will be ongoing along 131st Street between Parkside Drive and Cumberland Road. Updates on this project will be posted as they become available, and flaggers will be onsite to direct traffic.

Road Resurfacing

Scheduled to begin on the following roads:

  • Cumberland Road between 131st Street and 141st Street
  • Bridgewater Road
  • Aldenham Place
  • Doncaster Court
  • Burning Ridge Lane
  • Hamilton Pass